Diaphragm Wall Construction

Description :

  • The caterpillar band crane equipped with the flowing tubing head pressure shell is applied for excavation.
  • The trench is filled with slurry, mixture of water and bentonite or polyacrylamide, all the time to prevent collapse.
  • Whenever the design length is reached, the supersonic wave examination is conducted, Install rebar cage and cast the concrete will be proceed later on.