Projects

MRT System

Taipei MRT System Neihu Line Project No. CB420
Tachih Station and Tunnel

  • Client

    East District Project Office, Department of Rapid Transit Systems, TCG

  • Architect / Engineer

    China Engineering Consultants, Inc.

  • Location

    Tachih ,Taipei

  • Year of Completion

    2007

  • Structure

    Station:
    Underground R.C. structure with diaphragm wall of 1.0m thick, 37.0m deep

    Tunnel:
    Precast R.C. lining

  • Type of Work

    Station:
    Two-story MRT underground station, 163m in length x 22m in width

    Tunnel:
    Twin-bored tunnel with outer diameter of 5.6m constructed by TBM method, the minimum curvature radius R of 140m , total track length of 5901m ; Underground tunnel constructed by Cut & Cover method , 265m in length x 11~20m in width