Delhi Metro Phase-III Mukund Pur – Yamuna Vihar Corridor Contract CC-04

Project Type
MRT System
Location
New Delhi
Year
2015

Architect / Supervising Engineer

Geodata Engineering S. P. A

Client

Delhi Metro Rail Corporation Ltd.

Scope of work

  1. Underground section between Mukundpur Station (excluded) and Shalimar Bagh station (excluded) line chainage 110 m to 3,685 m
  2. Design and construction of tunnel by shield TBM
  3. Design and construction of tunnel by Cut & Cover
  4. Cut & Cover Underground Station at Azadpur
  5. Ramps at Mukund Pur and Shalimar Bagh for underground works

Highlights

Station: Cut & Cover method
Tunnel: Cut & Cover/TBM