Civil Engineering
Liantang/Heung Yuen Wai Boundary Control Point – Contract 6
- Project Type
- Bridge & Road
- Location
- New Territories
- Year
- 2018

Architect / Supervising Engineer
Supervision: AECOM Asia Co. , Ltd.
Client
Civil Engineering and Development Department, the Government of the Hong Kong Special Administrative Region


Scope of Work
The works include construction of a 4.6 km long dual two-lane trunk road (with about 0.6 km at grade roads, 3.3 km viaducts and a 0.7 km tunnel) connecting Sha Tau Kok Road Interchange to BCP, and the associated environmental mitigation measures, landscaping, drainage/sewerage, waterworks and utilities works.
The tunnel was excavated by drill & blast method. Large diameter concrete bored piles was adopted as the foundation of the viaducts, while using the pre-cast segmental method to erect the prestressed box girder of the viaducts.


Related Projects
Taipei MRT Circular Line Contract CF670
MRT System