Civil Engineering
N-WH Projects – Cross-harbor Tunnel Contract
- Project Type
- Tunnel & Underpass
- Location
- Nanzi District, Kaohsiung City
- Year
- 2027
Architect / Supervising Engineer
Design & Supervision: CECI Engineering Consultants Inc.
Project Management: Moh and Associates, Inc.
Client
Construction and Real Estate Service Center Armaments Bureau, Ministry of Defense
Structure
- Cut & Cover Tunnel: Reinforced concrete (RC) structure
- Water, electrical and environmental works
- Mechanical room works
Scope of Work
The “N-WH Plan” area is located in the north of the existing Zuoying military port, which belongs to the second port expansion project of the military port:
- Cut & Cover tunnel: the total length of the structure is about 1,500 m(including the main approach) and general mechanical and electrical works
- Revetment works: the total length is about 540 m
- Port dredging works: about 392,000 m3
- Mechanical and electrical works: environmental related power works for tunnel and mechanical room, air conditioning, tunnel ventilation and other mechanical equipment
Highlights
Military harbor project