Civil Engineering
Tainan Railway Underground Project Contract C211
- Project Type
- Tunnel & Underpass
- Location
- North District, Tanan City
- Year
- 2025

Architect / Supervising Engineer
Design & Supervision: CECI Engineering Consultants Inc.
Client
Southern Region Engineering Office, Railway Bureau,
Ministry of Transportation and Telecommunications
Structure
- Cut & Cover tunnel: RC structure
- Water, electrical and environmental works
- Temporary steel bridge crossing railway at Changrong Road
Scope of Work
The scope of this project is from Tainan Shenggong Girls’ High School to the vicinity of the level crossing of Dongfeng Road, with a total length of about 2,170 m.
- The main structure of the tunnel: the Cut & Cover tunnel (the main tunnel is 1,550 m, the approach tunnel is 150 m, and the length of the at-grade section is about 470 m) whose total length is about 2,170 m.
- Water, electrical and environmental works: pumping machinery room, tunnel ventilation shaft, escape room, special electrical/mechanical niches, cut & cover approach tunnel
Related Projects