Civil Engineering
Taipei MRT Banqiao Line Contract CP261
- Project Type
- MRT System
- Location
- Wanhua District, Taipei City
- Year
- 1999


Architect / Supervising Engineer
De Leuw Cather International, Inc.
Sinotech Engineering Consultants, Inc.
Client
Central District Project Office, Department of Mass Rapid Transit System,
Taipei City Government
Structure
Reinforced concrete (RC)
Scope of Work
- Station: Longshan Temple Station
- The total length of the shield tunnel is 3,297 m
Highlights
The station is constructed by Cut & Cover semi-top down method
The tunnel is constructed by soil pressure balance type TBM
Related Projects


Taipei MRT Circular Line Contract CF670
MRT System