Taipei MRT Circular Line Contract CF670A
- Project Type
- MRT System
- Location
- Wenshan District, Taipei City
- Year
- 2032
Architect / Supervising Engineer
Design: CECI Engineering Consultants Inc.
Supervision: The 10th Site Office, Second District Project Office, Department of Rapid Transit Systems, Taipei City Government
Client
Second District Project Office, Department of Rapid Transit Systems,
Taipei City Government
Structure
- Underground MRT station
- Shield tunnel
- Water, power and environmental work
Scope of Work
CF671
- Y01 station (underground 2-story island platform station with a length of 223m), Y1A station (underground 4-story island platform station with a length of 99m)
- Shield tunnel (Y01~Y1A/937m, Y1A~Y2A/940m)
CF624H
- Water, power, and environmental works for station facilities and shield tunnel section