Skip to content

Civil Engineering

Taipei MRT Nangang Line Contract CN256

Project Type
MRT System
Location
Xinyi District, Taipei City
Year
1999

Architect / Supervising Engineer

Sinotech Engineering Consultants, Inc.

Client

East District Project Office, Department of Rapid Transit System,
Taipei City Government

Structure

Reinforced concrete (RC)

Scope of Work

  1. Station: Sun Yat-sen Memorial Hall Station
  2. The total length of the shield tunnel is 1,920 m

Highlights

The station is constructed by Cut & Cover semi-top down method
The tunnel is constructed by soil pressure balance type TBM

Related Projects

You are now opening an external address

The website information you will be accessing is provided by another organization or vendor. Please press Continue to go to

CEC 80th Anniversary

CEC 80th Logo

CEC was founded in 1945, a challenging time full of uncertainty. Through eight decades of change, CEC has navigated the challenges of each era, always seeking opportunities to break through and progress further. As we enter this next chapter, we return to our founding aspiration – to remember why we began, and to know how we shall move forward. To embody this aspiration, we deliberately made our corporate identity understated. It serves as a reminder that our legacy is not about resting on past success, but about continuing to create value for our clients and societies and moving forward.


Our founding aspiration— roots us in times of change, nurtures our values and sustains our growth, lights the path ahead and fuels the will to move forward.


CEC Line pattern