Civil Engineering
Taipei MRT Nangang Line Contract CN256
- Project Type
- MRT System
- Location
- Xinyi District, Taipei City
- Year
- 1999


Architect / Supervising Engineer
Sinotech Engineering Consultants, Inc.
Client
East District Project Office, Department of Rapid Transit System,
Taipei City Government
Structure
Reinforced concrete (RC)
Scope of Work
- Station: Sun Yat-sen Memorial Hall Station
- The total length of the shield tunnel is 1,920 m
Highlights
The station is constructed by Cut & Cover semi-top down method
The tunnel is constructed by soil pressure balance type TBM
Related Projects
Taipei MRT Circular Line Contract CF670