Skip to content

Civil Engineering

Taipei MRT Wanda Line Contract CQ842

Project Type
MRT System
Location
Zhongsheng District, Taipei City
Year
2025

Architect / Supervising Engineer

CECI Engineering Consultants, Inc.

Client

Second District Project Office, Department of Rapid Transit Systems, Taipei City Government

Structure

Station: 1 underground three-story island station, the length of the station is 124.8 m (including diaphragm wall), the excavation depth is 25.55 m (excluding the collecting well), and the width of the station is 20.75 m (diaphragm wall included in general sections)

Tunnel: Divided into two sections and four shield tunnels: inner diameter =5.6 m, ring thickness =25 cm, total length 1,637 m

Scope of Work

Cultural relics rescue, underground MRT station, TBM tunnels

Related Projects

You are now opening an external address

The website information you will be accessing is provided by another organization or vendor. Please press Continue to go to