Skip to content

You are now opening an external address

The website information you will be accessing is provided by another organization or vendor. Please press Continue to go to

Continue

Civil Engineering

Taipei MRT Contract CQ840

Project Type
MRT System
Location
Zhongzheng District, Taipei City
Year
2025

Architect / Supervising Engineer

Design:
CECI Engineering Consultants Inc.

Supervision:
2nd Site Office, 2nd District Project Office, Department of Rapid Transit Systems, Taipei City Government,
1st Site Office of Water/Power/Environmental
CECI Engineering Consultants Inc.

Client

Second District Project Office, Department of Rapid Transit Systems,
Taipei City Government

Structure

Underground MRT station

Scope of Work

Underground MRT station, shield tunnel, water and electrical and environmental works, elevator and escalator.

  1. Station:
    • LG01 station is an island platform station with 2 underground floors, length: 315 m (including crossover 145 m), width: 19.05 m, excavation depth: 20.37 m
    • LG03 station is an island platform station with 2 underground floors, length: 155 m, width: 20.35 m
    • central turn-out lane: underground 1 floor structure, length: 295 m, width: 18.8 m, excavation depth: 17.17 m
  2. Tunnel: inner diameter 5.6 m, ring thickness =25 cm, total length 1,674 m
  3. The building:
    New construction of MRT Complex at LG03 Station Entrance B:
    • Zhongyi Education Building: 1 floor underground and 6 floors above ground
    • MRT exit/entrance co-construction facilities: 3 floors underground, 2 floors above ground (connecting Social Welfare Building)
    • New building works of new development area & LG03 Station entrance A

Related Projects